Statics & dynamics of buildings

 
Complex – LEGNER hotel, Zvánovice

Location: Zvanovice, Ondrejov
Architect: Quadra project s.r.o.
Client: LEGNER holding, spol. s.r.o.
Implementation of project: 02/2008
Activities implemented: Complete static element of project documentation
Construction time: 2009
Bungalows for hotel accommodation located in Zvánovice, near the town of Ondřejov. The bungalows are simple rectangular structures measuring 4.4 x approx. 7m and are situated adjacent to each other in two rows, with each row containing eight structures. Besides these two rows, there are three separate buildings in the complex. The buildings are of wood construction using the Platform Frame column system.

Grandhotel Zlaty lev

Location: Gutenbergova st., Liberec
Architect: MS Architektura a design
Client: Conradian, a.s.
Implementation of project: 2008
Activities implemented: Static element of the project for implementation of construction
Construction time: 2009
Comprehensive renovation of an existing building, its conversion into a hotel and operational connection to the neighbouring Grandhotel building. During the renovation, steel with a wood beam was used to replace the inadequate wood-joist ceilings. The existing roof was rebuilt (bracing) and the layout of the attic space was modified to create more open space. The building’s walls were secured with steel rods. An elevator was installed in the building, which is located in a historical landmark zone.

 

Finished projects

The new Municipal Office in Dolni Mecholupy 2009-06-30

A newly constructed building which has two above-ground and one subterranean floor.

 

Grandhotel Zlaty lev 2009-01-20

Comprehensive renovation of an existing building, its conversion into a hotel and operational connection to the neighbouring Grandhotel building.